Energiequelle GmbH commissions wind turbine in Ludwigsfelde

An Enercon E-138 will supply around 5,000 households in future
08.01.2025, Ludwigsfelde (Germany)
Press ReleaseWind

Energiequelle GmbH has put a wind turbine into operation in Ludwigsfelde. An Enercon E-138 with a hub height of 160 metres was erected on a landfill site in the Brandenburg district of Teltow-Fläming. The turbine has an output of 4.2 MW and produces electricity for around 5,000 households.

Approval for the project was granted in March 2023. Following a rejected appeal and legal action, construction of the turbine was able to begin in February last year. The plant has now successfully fed its first kilowatt hour into the grid.

Erik Klaus, Project Manager at Energiequelle GmbH, is delighted that the plant is now connected to the grid: ‘The commissioning of the new wind turbine is a significant milestone. The successful realisation shows the determination and commitment of everyone involved.’

The turbine is the 808th wind turbine erected by Energiequelle. Since its foundation in 1997, the company has connected more than 1,700 MW to the grid across Europe.